TABLE-Swiss nuclear plant outages and restarts

Dec 7 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked*** REACTOR NAME CAPACITY TIME PERIOD OPERATOR

Faulty Areva fuel rods sent to nuclear reactors, Swiss plant closed

PARIS/ZURICH, Nov 17 French nuclear group Areva delivered defective fuel rods for nuclear reactors but said on Friday that there was no safety risk.

TABLE-Swiss nuclear plant outages and restarts

(Gives some retroactive reports for Leibstadt earlier this year from most recent EEX website update) Nov 9 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked***

TABLE-Swiss nuclear plant outages and restarts

(Gives Leibstadt's possible outage end-date in 2017 and new dates for 2018, according to EEX website) Nov 8 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked***

TABLE-Swiss nuclear plant outages and restarts

(Leibstadt operator says to delay restart until end of December) Nov 8 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked*** REACTOR NAME CAPACITY

Alpiq looks to sell assets to rein in debt - sources

* To offer majority stakes in 3 money-making businesses - sources

TABLE-Swiss nuclear plant outages and restarts

(Leibstadt operator says to add around 10 days to outage, probably to Nov 17) Oct 31 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked*** REACTOR NAME

TABLE-Swiss nuclear plant outages and restarts

(Leibstadt operator says outage going according to plan so far, no change to restart date) Oct 19 The following table lists maintenance outages and unscheduled stoppages at Swiss nuclear power plants. Maintenance usually takes place in the spring and summer. Ownership of the plants is detailed under (1,2,3...) Please click on the link at the bottom to access the data. New content is marked*** REACTOR

Swiss stocks - Factors to watch on Oct 10

ZURICH, Oct 10 The Swiss blue-chip SMI was seen opening flat at 9,261 points on Tuesday, according to premarket indications by bank Julius Baer.

BRIEF-Alpiq Holding acquires Lundy Projects Ltd

* LUNDY PROJECTS LTD., IS A SPECIALISED SUPPLIER OF CATENARY SYSTEMS AND SIGNALLING STRUCTURES IN RAILWAY INFRASTRUCTURE SECTOR IN UK